We handed over the revitalized hall in the Tatra area

Before the renovation, the hall was a warehouse. Now the premises will be used for special and technically demanding modifications of Tatra vehicles, which previously affected the fluidity of the main production line.

  • In the affected part of the hall, all the equipment (HVAC, piping, electrical wiring) has been dismantled.
  • Subsequently, the internal walls of the hall were repaired, the roof of the hall including the roof skylight was repaired and a new floor was made including an assembly pit, the building was insulated with mineral wool sandwich panels and also insulated with polystyrene 100 mm thick including plaster.
  • New electrical wiring and lighting were installed.
  • Newly installed hot water heating of the hall, air conditioning and piping of air and corgon.
    Inside the hall a new vestibule (overhead storage, men/women's toilet, cleaning room and rest room are built.

Contracting authority: TATRA TRUCKS a.s.
Date of execution of the work: 22.04.2024 - 30.09.2024 

 

23. 10. 2024 Interest, News

This website uses cookies.

We use cookies to personalize content and ads, provide social media features and analyze our traffic. We also share information about the use of our site with our social media, advertising and analytics partners. They may use the data together with other information they collect about you while using their services.